File #: RES 2020-026    Name: SR7 Median Beautification Bid No. 01-08-20-11
Type: Resolution Status: Passed
File created: 1/22/2020 In control: City Commission
On agenda: 2/27/2020 Final action: 2/27/2020
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE AN AGREEMENT WITH VISUALSCAPE, INC. FOR STATE ROAD 7 MEDIAN BEAUTIFICATION PURSUANT TO BID NO. 01-08-20-11.
Sponsors: Public Works Department
Indexes: Agreement, Bid, FDOT, Grant, Median Enhancements, Resolution, SR7/US441
Attachments: 1. RESOLUTION 2020-026-SR7 Median Beautification-Bid No. 01-08-20-11, 2. AGREEMENT-SR7 Median Beautification-Bid No. 01-08-20-11, 3. BACKUP-Terms & Conditions-SR7 Medians-Bid No. 01-08-20-11, 4. BACKUP-Vendor Bid Response-SR7 Medians-Bid No. 01-08-20-11, 5. BACKUP-Tabulation-SR7 Medians-Bid No. 01-08-20-11
Related files: RES 2018-173

AGENDA ITEM REPORT

TITLE:

title

A RESOLUTION AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE AN AGREEMENT WITH VISUALSCAPE, INC. FOR STATE ROAD 7 MEDIAN BEAUTIFICATION PURSUANT TO BID NO. 01-08-20-11.

 

body

BACKGROUND:

The purpose of the Invitation for Bid is to contract with a qualified Florida Department of Transportation approved Landscape Contractor to enhance the State Road 7 medians from Cullum Road to just south of the Sawgrass Expressway.  The project consists of the installation of an irrigation system, decorative brick pavers, trees, shrubs, groundcover, and sod.  The City was successful in obtaining a Florida Highway Beautification Council Grant in the amount of $100,000 to partially fund these improvements, and the City of Coral Springs has agreed to share in the ongoing maintenance costs. 

DISCUSSION:

On December 1, 2019, the City issued one hundred seventy eight (178) electronic invitations to bid for the State Road 7 Median Beautification project. Six (6) responsive submittals were received from the following contractors: 1) VisualScape, Inc. ($486,702.35); 2) Landscape Service Professionals, Inc. ($529,148.00);  3) MBR Construction, Inc. ($647,640.00); 4) Green Construction Technologies, Inc. ($648,982.00); 5) Arazoza Brothers Corp. ($687,105.70); and 6) SFM Services, Inc. ($706,131.55).  Staff recommends awarding the contract to the lowest responsive bidder, VisualScape, Inc. for the total bid amount of $486,702.35.

RECOMMENDATION:

Staff recommends approval of this resolution.

FISCAL IMPACT:

REVENUES:                                                               $ 0

EXPENDITURES:                     $ 486,702.35

BUDGETED?                                                               Yes

NOTES:                     Funding is available from Account Nos. 1171541-6723 and 6571541-6723, State Road 7 Median Beautification CIP.