Legislation Details

File #: RES 2026-157    Name: Comprehensive Street Improvements Phase III Design
Type: Resolution Status: Agenda Ready
File created: 9/17/2026 In control: City Commission
On agenda: 10/8/2026 Final action:
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE A WORK AUTHORIZATION AND THE MAYOR, OR DESIGNEE, TO EXECUTE THE COUNTY SURTAX CONSULTANT AGREEMENT WITH KIMLEY-HORN AND ASSOCIATES, INC. FOR SURTAX PROJECT RMCOCO-003 TO PROVIDE DESIGN, PERMITTING, AND BIDDING SERVICES FOR THE COMPREHENSIVE STREET IMPROVEMENTS PHASE III PROJECT IN ACCORDANCE WITH RFQ NO. 07-29-25-11.
Indexes: Comprehensive Street Improvements, Resolution, Surtax, Utilities and Engineering, Work Authorization
Attachments: 1. RESOLUTION 2026-157-CSI Phase III Project Design, 2. WORK AUTHORIZATION-CSI Phase III Project Design, 3. EXHIBIT A-County Surtax Consultant Agrmt-CSI Phase III Project Design, 4. EXHIBIT B-Kimley-Horn Proposal-CSI Phase III Project Design, 5. BACKUP-Resolution 2026-072-Surtax Funding Agreement, 6. BACKUP-Resolution 2025-147-Kimley-Horn Master Agreement
Related files: RES 2025-147, RES 2026-072
Date Action ByActionResultAction DetailsMeeting DetailsMedia
No records to display.
AGENDA ITEM REPORT
TITLE:
title
A RESOLUTION AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE A WORK AUTHORIZATION AND THE MAYOR, OR DESIGNEE, TO EXECUTE THE COUNTY SURTAX CONSULTANT AGREEMENT WITH KIMLEY-HORN AND ASSOCIATES, INC. FOR SURTAX PROJECT RMCOCO-003 TO PROVIDE DESIGN, PERMITTING, AND BIDDING SERVICES FOR THE COMPREHENSIVE STREET IMPROVEMENTS PHASE III PROJECT IN ACCORDANCE WITH RFQ NO. 07-29-25-11.

body
BACKGROUND:
The City’s roadway infrastructure has aged and requires ongoing rehabilitation as part of the City’s Comprehensive Street Improvements Program. Phase III of the project includes approximately ten (10) centerline miles of City roadways located north of the Sawgrass Expressway and will address milling and resurfacing, roadway reconstruction, roadway striping and signage, sidewalk improvements, and Americans with Disabilities Act (ADA) improvements. The City applied for Fiscal Year 2026 (FY26) formula-based surtax funding to support the design phase of the project, and Broward County approved funding for the project, identified as Surtax Project RMCOCO-003, pursuant to Resolution No. 2026-072.
DISCUSSION:
The City is committed to maintaining safe and reliable roadway infrastructure and addressing the ongoing rehabilitation needs of City roadways. To continue the Comprehensive Street Improvements Program, it is necessary to proceed with the design of Phase III, which includes approximately ten (10) centerline miles of roadway improvements north of Sawgrass Expressway. The City has an agreement with Kimley-Horn and Associates, Inc. to provide general professional engineering services pursuant to RFP No. 07-29-25-11. Kimley-Horn has submitted a proposal, attached as Exhibit “B,” to provide the required design, permitting, and bidding services for a total cost of $161,000. In addition, a consultant agreement is required by Broward County for Surtax projects, which is included as Exhibit “A.”
RECOMMENDATION:
Staff recommends approval of this...