File #: RES 2025-103    Name: Hilton Road Water Tank Relining IFB No. 05-28-25-11
Type: Resolution Status: Agenda Ready
File created: 6/18/2025 In control: City Commission
On agenda: 7/10/2025 Final action:
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE AN AGREEMENT WITH CROM, LLC D/B/A CROM COATINGS AND RESTORATIONS TO PROVIDE LABOR AND MATERIAL FOR THE RELINING OF THE WATER STORAGE TANK LOCATED AT 4801 HILTON ROAD PURSUANT TO INVITATION FOR BIDS (IFB) NO. 05-28-25-11.
Indexes: Agreement, Capital Improvements, Invitation to Bid, Resolution, Utilities and Engineering, Water and Wastewater
Attachments: 1. RESOLUTION 2025-103-Hilton Water Storage Tank Relining-IFB 05-28-25-11, 2. EXHIBIT A-Agreement-IFB 05-28-25-11, 3. BACKUP-Terms and Conditions-IFB 05-28-25-11, 4. BACKUP-Add Alternate 1-IFB 05-28-25-11, 5. BACKUP-Vendor Bid Response-IFB 05-28-25-11, 6. BACKUP-Bid Tabulation-IFB 05-28-25-11
Date Action ByActionResultAction DetailsMeeting DetailsMedia
No records to display.

AGENDA ITEM REPORT

TITLE:

title

A RESOLUTION AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE AN AGREEMENT WITH CROM, LLC D/B/A CROM COATINGS AND RESTORATIONS TO PROVIDE LABOR AND MATERIAL FOR THE RELINING OF THE WATER STORAGE TANK LOCATED AT 4801 HILTON ROAD PURSUANT TO INVITATION FOR BIDS (IFB) NO. 05-28-25-11.

 

body

BACKGROUND:

The City’s Hilton Road Water Storage Tank was originally designed and constructed in 1984.  The interior wall of the water storage tank was relined twelve (12) years ago to prevent leakage and maintain water quality.  The liner has surpassed its ten (10)-year useful life expectancy, and the water tank is now showing signs of stress and visible water leaks.  After investigation and localized repairs, it has been determined that the tank is in need of relining, which was included in the Fiscal Year 2025 (FY25) budget.

DISCUSSION:

 

On May 4, 2025, the City issued Invitation for Bids (IFB) No. 05-28-25-11 for construction services related to the relining of the Hilton Road Water Storage Tank project.  On May 28, 2025, the bid closed with one (1) responsive and responsible bidder, CROM, LLC, in the amount of $937,600.00, including the addition of Alternative #1 to repair the corroded DIP lines. The full solicitation, including plans and specifications, is available at the following link: <https://coconutcreek.ionwave.net/PublicDetail.aspx?bidID=467&SourceType=2>

 

City staff thoroughly reviewed the bid for compliance, and no issues were found.  A ten percent (10%) contingency has been included in the budget to account for unseen conditions for a total amount of $1,031,360.00.

RECOMMENDATION:

Staff recommends approval of this resolution.

FISCAL IMPACT:

REVENUES:                                          $ 0

EXPENDITURES:                     $ 1,031,360.00, including 10% contingency

BUDGETED?                                          Yes

NOTES:                     Funding is available from Account No. 4291533-6513, Rehabilitation of Water Storage Tanks CIP.