File #: RES 2026-007    Name: Fire Station 113 CMAR Phase 1 Pre-construction Services
Type: Resolution Status: Agenda Ready
File created: 12/17/2025 In control: City Commission
On agenda: 1/8/2026 Final action:
Title: A RESOLUTION AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE AN AGREEMENT WITH JAMES B. PIRTLE CONSTRUCTION COMPANY, INC. D/B/A PIRTLE CONSTRUCTION COMPANY FOR CONSTRUCTION MANAGER AT RISK PHASE 1 PRE-CONSTRUCTION SERVICES FOR FIRE STATION 113 AND FIRE ADMINISTRATION BUILDING PURSUANT TO LOI NO. 11-18-25-10.
Indexes: Contract, Fire Station 113, LOI, Public Works, Resolution
Attachments: 1. RESOLUTION 2026-007-CMAR Phase 1 Fire Station 113 & Fire Admin, 2. EXHIBIT A-CMAR Phase 1 Fire Station 113 & Fire Admin, 3. BACKUP-Terms & Scope-CMAR Phase 1 Fire Station 113 & Fire Admin, 4. BACKUP-Vendor Submittal-CMAR Phase 1 Fire Station 113 & Fire Admin, 5. BACKUP-Evaluation Final Ranking-CMAR Phase 1 Fire Station 113 & Fire Admin, 6. BACKUP-Presentation-CMAR Phase 1 Fire Station 113 & Fire Admin
Date Action ByActionResultAction DetailsMeeting DetailsMedia
No records to display.
AGENDA ITEM REPORT
TITLE:

title
A RESOLUTION AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE AN AGREEMENT WITH JAMES B. PIRTLE CONSTRUCTION COMPANY, INC. D/B/A PIRTLE CONSTRUCTION COMPANY FOR CONSTRUCTION MANAGER AT RISK PHASE 1 PRE-CONSTRUCTION SERVICES FOR FIRE STATION 113 AND FIRE ADMINISTRATION BUILDING PURSUANT TO LOI NO. 11-18-25-10.

body
BACKGROUND:
Fire Station 113 currently operates out of a temporary trailer located just south of Wiles Road and east of State Road 7. A new permanent fire station is needed to serve the upcoming MainStreet Area. Additionally, the City's Fire Administration staff is currently working out of leased office space and needs a permanent facility. The City currently owns a vacant ten (10) acre parcel of land along Cullum Road, and the proposed building will be constructed on a portion of this land.
DISCUSSION:
On October 19, 2025, the City issued Request for Letters of Interest (LOI) No. 11-18-25-10 to contract with a qualified general contractor for Construction Manager at Risk (CMAR) pre-construction phase and construction phase services to build the new fire station and administration facility.
The City issued seven hundred and forty-four (744) electronic invitations for the project. Five (5) responsive submittals were received from the following firms: (1) CORE Construction Services of Florida, LLC; (2) Gulf Building, LLC; (3) Kaufman Lynn Construction, Inc.; (4) Pirtle Construction Company; and (5) Waypoint Contracting, Inc.
A selection committee consisting of Harry Mautte, Public Works Director; Brian Rosen, Public Works Assistant Director; Lizet Aguiar, Resilient Design and Development Assistant Director; Eileen Cabrera, Senior Engineer; and Brian Blizzard, Fire Chief, evaluated the submittals based upon the LOI criteria. The selection committee ranked the five (5) responsive firms, and the top three (3) ranked companies were asked to conduct presentations to the committee. Upon completion of the presentations,...

Click here for full text