Title: *AL HENDRICKSON TOYOTA A/K/A TOYOTA COCONUT CREEK: A PLANNED MAINSTREET DEVELOPMENT DISTRICT (PMDD) SITE PLAN APPLICATION TO REDEVELOP THE EXISTING AL HENDRICKSON TOYOTA AUTOMOBILE DEALERSHIP LOCATED AT 5201 WEST SAMPLE ROAD. (QUASI-JUDICIAL)(PUBLIC HEARING)
Indexes: Discussion Item, Planning and Zoning, PMDD, Site Plan Modification
Code sections: 13-548, - Site Plan Review Requirements
Attachments: 1. BACKUP-Aerial Photo-Al Hendrickson Toyota Site Plan, 2. BACKUP-Application-Al Hendrickson Toyota Site Plan, 3. BACKUP-Exhibits-Al Hendrickson Toyota Site Plan, 4. BACKUP-DRC Reports-Al Hendrickson Toyota Site Plan, 5. BACKUP-Community Outreach-Al Hendrickson Toyota Site Plan, 6. BACKUP-Trip Generation Statement-Al Hendrickson Toyota Site Plan, 7. BACKUP-New Vehicle Test Drive-Al Hendrickson Toyota Site Plan, 8. BACKUP-Applicant Presentation-Al Hendrickson Toyota (New)
Related files: 26-022, 26-048

AGENDA ITEM REPORT

TITLE:

 

title

*AL HENDRICKSON TOYOTA A/K/A TOYOTA COCONUT CREEK:  A PLANNED MAINSTREET DEVELOPMENT DISTRICT (PMDD) SITE PLAN APPLICATION TO REDEVELOP THE EXISTING AL HENDRICKSON TOYOTA AUTOMOBILE DEALERSHIP LOCATED AT 5201 WEST SAMPLE ROAD. (QUASI-JUDICIAL)(PUBLIC HEARING)

body

BACKGROUND:

The applicant, Jay Doucette, Spring Engineering, Inc., on behalf of Coconut Creek Automotive Management, LLC, is requesting Planned MainStreet Development District (PMDD) Site Plan approval to redevelop an existing automobile dealership located at 5201 West Sample Road (Al Hendrickson Toyota a/k/a Toyota Coconut Creek).

The property originally received Special Land Use and Site Plan Approval in 1989 for the construction of the Al Hendrickson Toyota Dealership, with subsequent applications over the years, resulting in the configuration that exists today. 

In December of 2004, the City Commission adopted the MainStreet Design Standards (MSDS), which serve as the overall design framework for future projects within the MainStreet Project Area (MSPA) but do not have the effect of rezoning the property. Therefore, development applications within the boundaries of the MSPA are required to rezone to PMDD when redeveloping the site and be reviewed for consistency with the design standards. As such, a rezoning from B-4 (Regional Shopping District) to PMDD is required to comply with the MSDS and PMDD rezoning requirements.

The applicant has concurrently filed an application for Rezoning to redevelop the site and expand the existing Toyota dealership.

Application and Site Information

 

 Application No.:

PZ-24040003

 Applicant/Agent:

Jay Doucette - Spring Engineering Inc

 Property Owner:

Coconut Creek Automotive Management, LLC

 Location: 

5201 West Sample Road

 Folio No.:

484218030010

 Abbr. Legal Description:

COMMERCE CENTER OF COCONUT CREEK 131-30 B TRACT A LESS POR FOR R/W DESC IN OR 18085/503

 Net Area of Property: 

12.3 +/- acres 

 Existing Use: 

Commercial/Automobile Dealership 

 Zoning: 

B-4 (Regional Shopping District)  

 Future Land Use:

Regional Activity Center (RAC) 

 Plat Restriction: 

487,270 square feet of commercial; 323,389 square feet of office; 199,538 square feet of industrial

 

DISCUSSION:

​​Project Description 

The existing site consists of two (2) distinct structures that include sales and showroom facilities, vehicle service and car wash facilities, three (3) inventory display areas along Sample Road, and an expansive surface parking lot with just over 900 parking spaces for customers and vehicle inventory. The total existing dealership is approximately 39,300 square feet.

The applicant proposes to redevelop the site by expanding the existing Toyota dealership from approximately 39,300 square feet to approximately 98,000 square feet of sales, showroom, and service area, with an approximately 157,300 square foot parking garage and carwash/detail facility. The proposed redevelopment will utilize portions of the existing building while introducing new floor area to the site. The proposal includes a six (6)-story parking garage with roof-top parking, consisting of 568 parking spaces that will be used for vehicle inventory storage.

The existing parking configuration and landscaping will be amended to accommodate the additional building footprint and bring the site further into compliance with the Land Development Code and MSDS regulations. However, the landscape plan as designed features a deficit of thirty-seven (37) trees required by Section 13-443(3), which requires one (1) tree for every 1,000 square feet of landscape area on the site. The landscape plan shows the use of individual palms counted as meeting one (1) required tree, but the code requires that when using palms to count toward minimum tree requirements, a minimum ratio of three (3) palms for every one (1) shade tree required must be provided. Based on the landscape plan submitted, the site is short thirty-seven (37) trees. 

However, this is a redevelopment of an existing site, and the applicant is providing adequate landscaping throughout the site as required by all of the other portions of the landscape code. With that consideration in mind, in addition to the limited space available to support that many additional trees, the applicant, as an alternative to planting these additional palms on site, may mitigate this requirement by paying approximately $800 per tree, or $29,600, into the City’s Tree Preservation Trust Fund.

The uses on the property will be expanded but will not change in nature. The applicant is proposing site features that include a perimeter greenway connection along Sample Road, improvements along Banks Road, and enhanced landscape buffers along all frontages.

The featured design reflects Toyota’s current branding image, and the parking garage incorporates metal screening panels and artificial plant material to conceal parked vehicles and soften the massing of the garage façades. These treatments are intended to enhance visual quality, reduce the perceived scale of the structure, and integrate the garage, required by the MSDS, more cohesively with the overall site design.

Supporting the following Sustainable Elements:

Action 1.1: Commitment to pursue LEED v4 for New Construction Certification.

 Action 1.6: Comprehensive sign that illustrates all green technology used within the Site/Building, e.g., pervious pavement, trash recycling, no smoking signs, walk off mats, EV parking/charging,

Action 2.1: The proposed Toyota Dealership development will replace the canopy removed from the building addition on site. Additional trees will be planted in the proposed landscape islands to improve tree canopy within the site.

Action 2.2: Material that has a high reflection value will be utilized for the roofs on the subject property. The roof will be a white TPO membrane roofing material with an SRI of 94, which will minimize any additional heat-island effects on the site.

Action 3.1: Electric vehicle charging stations shall be provided in the new shop and within the customer parking lot in front of and adjacent to the sales building to support alternative fuel vehicle use.

Action 5.1: During construction, the General Contractor will segregate all construction waste generated and recycle the appropriate materials. After occupancy, the Applicant will continue recycling paper, metal, tires and oil. The Applicant will continue to implement a recycling program in the day-to-day operation of the dealership and during construction.

Action 5.3:  During construction, the General Contractor will segregate all construction waste generated, and recycle the appropriate materials. The solid waste hauler will provide recycling service during construction. Fifty to seventy-five (50-75%) of the demolition and debris will be diverted away from the landfill.

Action 6.2: There are four (4) bus stops within four (4) miles of the showroom’s main entrance. Also, a greenway trail will be provided along Sample Road to promote pedestrian and bicycle travel. The sidewalk along Sample Road is 12’ wide. Bike racks and bike lanes are proposed as part of the site improvements to promote bicycle mobility.

Action 6.4: Twelve (12) parking spaces will be designated and reserved for alternative  fuel vehicles within customer parking areas.

​Public Involvement

As part of the application review process, the applicant held a community meeting on January 20, 2026, at 6:00 p.m. at Al Hendrickson Toyota, located at 5201 West Sample Road, to present the project and provide an opportunity for questions or comments. The community meeting summary and presentation materials have been included in the back up for this item. No members of the public attended the meeting.

RECOMMENDATION:

Based on its review, staff finds that the proposed Site Plan meets the Site Plan Review criteria of the Land Development Code, the requirements of the proposed Al Hendrickson PMDD, and is consistent with the applicable goals, objectives, and policies of the City’s Comprehensive Plan. Accordingly, staff recommends approval of the Site Plan application, subject to the following conditions:

1.                     Outstanding DRC comments remain effective throughout the development review process and must be addressed prior to issuance of a building permit unless otherwise stated therein.​

2.                     Prior to building permit issuance, the Public Art requirement shall be satisfied by paying $94,250.60 into the City’s Public Art fund or provide Public Art in compliance with Section 13-143 through 13-146, which requires Commission approval. The amount may be adjusted if the gross floor area, as provided herein is amended.

3.                     Prior to building permit issuance, the applicant shall pay to the City all outstanding landscape cost recovery fees.

4.                     Prior to building permit issuance, the applicant shall pay all applicable impact fees per Section 13-118 of the City’s Land Development Code.

5.                     The applicant shall permit the Resilient Design and Development Department to periodically inspect the artificial plant material on the garage façade to ensure the material remains in good condition and continues to maintain its intended design integrity and aesthetic value. If the Director of Resilient Design and Development determines that the artificial plant material is no longer in acceptable condition, the Director shall notify the property owner in writing of such findings, and the artificial material shall be replaced at the applicant’s expense within an agreed upon time, not to exceed three (3) months.

6.                     Test Drive route shall not deviate from the route as approved by the site plan application as identified on the “New Vehicle Test Drive” exhibit dated December 23, 2025. 

7.                     Lighting fixtures located on the roof deck of the parking garage shall not extend beyond the height of the parapet wall.  

8.                     Prior to the issuance of the Certificate of Occupancy, the kaleidoscope canopy style bus shelter shall be installed, inspected and accepted by the City.  

9.                     Prior to issuance of a Certificate of Occupancy for a new structure, the property owner shall construct, irrigate, and landscape the Banks Road median and enter into a Maintenance Agreement with bond with the City for a minimum of one (1) year.

10.                     Prior to the issuance of the Certificate of Occupancy, if the City is required to enter into or amend a Maintenance Memorandum of Agreement (MMOA) with FDOT, the applicant will enter into a reciprocal perpetual maintenance agreement with the City, where the maintenance obligation for the proposed public improvements (bus shelter, shared use pathway, trash receptacle, landscaping, etc.) along Sample Road, will be assigned to the Property Owner and their successors. 

11.                     Upon the Mainstreet at Coconut Creek project completion of the construction of the reclaimed water main along Banks Road, the property owner shall connect to this public reclaimed water supply for irrigation to abide by Chapter 62 of the FAC and Broward County Article II - Water and Sewer Connection Ordinance.

12.                     The three vehicle display areas adjacent to Sample Road shall be permitted as illustrated on the site plan.

13.                     Loading and unloading operations will be restricted to the same business hours of operation established herein.

14.                     Loading vehicles shall not wait on subject property or street right-of-way prior to opening hours.

15.                     No outdoor loudspeakers shall be allowed on site, except in connection with a surveillance security system.

16.                     Hours of Operation shall be limited to the following:

Sales: Monday - Saturday 8 a.m. to 9 p.m.

Sunday 10 a.m. to 9 p.m.

Service and Parts: Monday - Friday 6:30 a.m. to 8 p.m.

                                           Saturday 6:30 a.m. to 6 p.m.

                                           Sunday 7 a.m. to 4 p.m.

17.                     The applicant shall plant thirty-seven (37) trees on site or pay approximately $800 per tree, or $29,600, into the City’s Tree Preservation Trust Fund pursuant to the City’s Landscape Code, or a combination thereof. 

FISCAL IMPACT:  N/A